Import machine changeovers

Available on
  • Trial
  • Pro
  • Enterprise
Who can do this
  • Import machine changeoversRoles: AdministratorPermission: equipment:write

The machine changeovers import sets from a CSV file how many minutes a machine needs between work on one item and work on the next. Each row is one of the machine’s changeovers, from the work before to the work after, one way. A row whose machine and two sides match a changeover changes its minutes, and any other row adds one.

On the Equipment screen, open Actions on the Machines tab and click Import machine changeovers…. How a CSV import works explains the dialog, the file and its formats.

  • A side with a product only (fromProductSku or toProductSku) is any work of that product.
  • A side with a variant too (fromVariantSku or toVariantSku) is work of that variant only, which must be one of the product beside it.
  • The machine has no changeover between the two sides: the row adds one. It has one: the row changes its minutes. A changeover the file leaves out stays.

A changeover from a product to itself sets what switching between its variants takes. Where a machine has no changeover for two items, it takes its own changeover from its page.

unitNumber names a machine by its unit number, and the SKUs products and variants, each exactly. Import the machines, products and variants first.

ColumnFormatWhat it holdsExample
unitNumberRequiredImport keyTextThe unit number of the machine the changeover is onOV-01
fromProductSkuRequiredImport keyTextThe SKU of the product of the work before the changeoverBUREK
toProductSkuRequiredImport keyTextThe SKU of the product of the work after the changeoverBUREK
minutesRequiredWhole numberThe changeover in whole minutes, 0 or more: what the machine needs between the work before and the work after, this way round only30
fromVariantSkuImport keyTextThe SKU of one of the from product's variants, for a changeover from that variant only; when empty, from any work of the productBUREK-MEAT
toVariantSkuImport keyTextThe SKU of one of the to product's variants, for a changeover to that variant only; when empty, to any work of the productBUREK-SPINACH
  • A unitNumber that matches no machine: a machine without a unit number can’t be found by an import, so give it one on its page first.
  • A product that matches nothing, and a variant that isn’t one of the product beside it.
  • The same variant on both sides: work of one item needs no changeover.
  • Minutes below zero.
  • The same changeover twice in the file.