Change when a delivery is expected
- Available on
- Trial
- Pro
- Enterprise
- Who can do this
- Change a purchase order's expected day, or report late materialRoles: Administrator
Permission: purchasing:write - Open the Report page, beside purchasing:writeRoles: Administrator, Shift supervisor
Permission: exception:report or planning:execute
- Change a purchase order's expected day, or report late materialRoles: Administrator
When a supplier confirms a different day, change the expected day on the purchase order, or on one of its lines. werkplan doesn’t start a production order’s work before the purchased material it needs is there, so the day you enter moves the plan.
Change the day
Section titled “Change the day”- Open the purchase order from Purchase orders. It can be changed until it is Received or Cancelled.
- For the whole order, click Edit on General, pick the day under Expected and click Save. Lines without a day of their own follow it; a line with its own day keeps it.
- For one line of a goods order, open the line’s actions, click Edit line, pick the day under Expected and click Save. Leave it empty to follow the order’s day. The lines of outsourced work aren’t edited.
On the Report page, Late material gives one line of a placed order a later day in the same way, from wherever you are. The page opens for people with exception:report or planning:execute.
How the day reaches the plan
Section titled “How the day reaches the plan”What is outstanding on a placed order’s line is an open purchase, expected on the line’s own day, else the order’s. Each time a scenario or a re-plan is made, werkplan works out every open production order’s material-ready time: material from a purchase is there from the start of the day after it is expected. A day that has passed counts as today, so the order waits until tomorrow. The work of an order not yet started doesn’t start before its material-ready time; an order the shop floor has started never waits for its material. See What holds work back.
A draft counts as nothing until you place it, and a placed line with no day isn’t counted as coming at all.
What a later day does
Section titled “What a later day does”With a master plan in force, werkplan works out the material again as soon as you save. Each production order whose work in the master plan starts before its material is there is named in one Late material exception, with the time its material is ready:
- the planners are told, and the open re-plan takes it in and plans the orders’ work after their material;
- the master plan stays as it is until a planner promotes the re-plan;
- withdrawing the exception puts the day back as it was.
When no planned work starts before the material is there, nothing is reported.
What an earlier day does
Section titled “What an earlier day does”An earlier day opens no exception. When it moves a production order’s material-ready time, Show changes on the Master plan screen lists the order, as Material ready with its old and its changed time, scenarios made before go out of date, and the next re-plan or scenario plans with the earlier day. When stock already covered the orders, nothing moves.
Good practice
Section titled “Good practice”- Enter the day the supplier confirms, not the day you hope for: planning trusts it.
- Give every placed line a day. A line without one reads No date and isn’t counted as coming: planning treats its material as not ordered, and waits the default supplier’s lead time for it instead.
- When a delivery is late, change its day as soon as you know, rather than leave a day that has passed: an overdue delivery counts as coming today, every day until it arrives.
See Purchase order.