Skip to content

The master plan and scenarios

Available on
  • Trial
  • Pro
  • Enterprise
Who can do this
  • See the master plan and every scenarioRoles: Administrator, Shift supervisor, EmployeePermission: schedule:read
  • Create, change, solve, delete or promote a scenario, and open the re-planRoles: AdministratorPermission: planning:execute
  • Try a draft orderRoles: AdministratorPermission: order:write

The master plan is the one production schedule in force: the plan the shop floor works from. It changes only when you promote a scenario, so nothing you try, and nothing that happens, moves work on the shop floor until a planner decides.

Your organisation has at most one master plan at a time. It says which operation runs on which machine, when, and, where the workforce schedule is published, who does it. Its production orders read Scheduled, and the Master plan screen shows it.

The master plan never changes by itself. When an order is added, a machine gets an unavailable time or an employee is away, the master plan stays as it was promoted. The Master plan screen counts these changes and Show changes lists them. Every master plan you replace stays on the Master plan history screen as it was. See Master plan.

A scenario is a copy of the plan to try something on. When you create one, it takes an input snapshot: all of today’s planning data (open production orders, routings, machines, tools, calendars, shifts and people) as it is at that moment. Changes to your data made later don’t reach it. You add changes to it, such as a machine failure or an absence, and solve it. Solving plans every open production order of its snapshot with its changes, and writes only the scenario’s own result.

Every planner sees every scenario, and none of them changes anything real. You compare a solved scenario with the master plan, then promote it or delete it. See Scenario.

Promote makes a solved scenario’s plan the master plan. It is the only way a plan goes into force:

  • the scenario’s plan becomes the master plan, and the one it replaces moves to the history;
  • the production orders it plans become Scheduled;
  • the changes you added to the scenario are saved as real data: a machine failure becomes the machine’s unavailable time, an absence the employee’s.

A scenario made before the master plan changed is out of date. When you promote it, werkplan first plans it again on today’s data and shows you that result to promote.

The re-plan is the one open scenario that takes in every exception reported, such as a machine down, an absence or a rush order. Re-plan on the Master plan screen opens it. It moves as little work as it can around the exceptions, and it changes nothing until you promote it, like any scenario. See Re-plan and When something happens.

A try plans a draft production order as if it were submitted, to answer “can we promise Friday?”. It shows when the order would finish against its due date, and it saves nothing. See Try a draft order before you promise a date.

Still stuck? Write to support@example.com.