Give a product its routing
- Available on
- Trial
- Pro
- Enterprise
- Who can do this
- Add and change a routing, its steps, tool requirements and additional employeesRoles: Administrator
Permission: product:write
- Add and change a routing, its steps, tool requirements and additional employeesRoles: Administrator
A product’s routing is the steps its production orders are made in, in order, each on a type of machine. werkplan plans a product’s orders only once its routing has steps and is Active; this page takes you there.
Before you start
Section titled “Before you start”- The product exists on the Products screen.
- Each step runs on an equipment type, such as Oven. Add the types on the Equipment screen first, or on the spot with the + beside the field.
- To be planned, a step needs at least one machine of its type with a capacity for the product, or a default capacity: see Add a machine.
Add the routing
Section titled “Add the routing”- Open the product’s page. Under Process, click Add routing.
- Enter a Name, such as Standard. A product has one production routing.
- If you like, enter a Description for your team. Planning doesn’t read it.
- Click Create routing.
The routing starts as Draft, so nothing is planned along it while you add its steps.
Add the steps
Section titled “Add the steps”Click Add step for each step, in the order the work runs, and click Add step in the dialog to save it. Drag a step to change the order later.
- Step name, such as Mixing. The dispatch list prints it.
- Equipment type: only machines of this type can run the step, and only those with a capacity for the product, or a default one.
- Processing time: how long a batch takes.
- Machine time takes each machine’s own figure, from its capacity for the product or its default capacity.
- Time per batch is minutes for one batch, whatever its size, such as 55 minutes of proofing.
- Rate per hour is how many units, in the variant’s base unit, are made in an hour.
- Either figure of the step’s own stretches with a machine’s efficiency: at 80 %, a batch takes 1.25 times as long.
- Buffer after (min): minutes the next step waits after this one, such as for cooling.
- Allow pause after this step: ticked, the next step may start any time after the buffer. Unticked, it follows at once, in the same working window, so no break or closed time falls between them.
- One person from start to finish: the step never changes hands at a shift change, so each of its operations must fit in one shift.
- Description: notes on how the step is done. Planning doesn’t read it.
A step has no setup time of its own: a machine’s setup is part of its capacity.
Add tools and extra people, if the work needs them
Section titled “Add tools and extra people, if the work needs them”- Tool requirements, on a step’s row: choose a Tool type and the Quantity each operation holds, and click Add. Each change saves at once. werkplan places an operation only when that many units of the type are free: see Tools.
- Add employee, under Additional employees: choose a Training and how many Employees with it each operation needs, from 1 to 100, and click Add. Every step of the routing then needs them at once, on top of the crew its machine asks for, such as a supervisor.
Make it active
Section titled “Make it active”- In the menu beside the routing’s name, click Edit routing.
- Set Status to Active.
- Click Save.
Scenarios and re-plans made from then on plan the product’s production orders along the routing. The master plan stays as it is until you promote one of them; meanwhile, Show changes on the Master plan screen lists the routing as New routing for a product that open orders make.
If something goes wrong
Section titled “If something goes wrong”A scenario lists each production order it couldn’t plan, with the reason:
| Reason | What to do |
|---|---|
| No active routing | Add the routing’s steps, or set it to Active |
| No machine can run it | Add a machine of the step’s equipment type, or give a machine a capacity for the product |
| Not enough tools | Add tool units of the type |
| Not enough trained employees | Train more people for the step, or put more of them on one shift |
| Longer than any working window | Lengthen the shift, or make the batch smaller |
| Steps that follow at once longer than any working window | Allow a pause after one of the steps, lengthen the shift, or make the batch smaller |
| One-person step longer than every unbroken stretch of a shift | Split the step, make the batch smaller, change the shifts, or untick One person from start to finish |
| Batch limits can’t be met | Change a machine’s batch limits for the product, or the order’s quantity |
What comes next
Section titled “What comes next”Give the product a bill of materials, so that its orders know what material they need: Set up a bill of materials. A variant that is made differently can add or replace steps on its own page: see Variant.
Still stuck? Write to support@example.com.