QA rejection
- Available on
- Trial
- Pro
- Enterprise
- Who can do this
- See an order's QA rejectionsRoles: Administrator, Employee
Permission: order:read - Record one on a task's page, or cancel oneRoles: Administrator, Shift supervisor
Permission: schedule:write - Record one on the Report pageRoles: Administrator, Shift supervisor
Permission: exception:report - Record one at a shop-floor terminalRoles: Administrator, Shop floor terminal
Permission: shopfloor:report
- See an order's QA rejectionsRoles: Administrator, Employee
A QA rejection records that part of a production order failed inspection at a routing step. It adds extra work to the order: the units are reworked, or replacements are made from the first step. The next plan plans that work, and the rejection resolves once it is done.
Where you record one
Section titled “Where you record one”- On a task’s page: Actions › Record a QA rejection, on a task in progress or completed. See Task.
- On the Report page: QA rejection, then the machine and the work on it, of the master plan’s work running or finished in the last day.
- At a shop-floor terminal, with Report a problem: the operator picks the work that failed inspection, how many were rejected, and Rework or Replace.
In the office, Record a QA rejection asks:
- Rejected quantity, in the order line’s unit, up to what can still be rejected. The dialog shows the Product, the Failed step, the Quantity and what Can still be rejected.
- Action: Rework redoes these units; Replace makes them again from step 1.
- For rework, the step to Start rework from step, the failed step if you leave it empty, or, when the product has a rework routing, a Rework routing, whose steps run before the line’s steps after the failed one. Not both.
- Reason: what failed inspection, kept with the rejection.
Click Record rejection. A terminal always reworks from the failed step.
werkplan refuses a rejection on work that isn’t in progress or completed, on a cancelled order, on the extra work of another rejection, and one that would reject more than the task’s quantity, less its scrap and its earlier rejections.
What it changes
Section titled “What it changes”- Extra work: the order gets the rework or the replacement as extra work. No task is made at once: the next plan, the re-plan or a scenario, plans it, and promote puts its tasks in force, marked Rework or Replacement.
- The order: a completed production order goes back to In Progress, and doesn’t complete again while the rejection is open.
- Stock: a replacement reserves material for the units made again. On an order whose output was received, a replacement writes the rejected units off.
- The re-plan: it is an exception, as it is always about work of the master plan. Every planner is told, and the open re-plan plans the extra work.
- Who is told: everyone with
order:writewho doesn’t plan is told a QA rejection was recorded, with the order.
You see an order’s QA rejections on its page, under QA rejections: the Product with the reason, where it Failed at, how many were Rejected, the Extra work, how much of it is Made, its Status and when it was Recorded.
Statuses
Section titled “Statuses”stateDiagram-v2 accTitle: QA rejection statuses accDescr: A QA rejection is recorded open. It resolves once its extra work has made the rejected quantity, or when its order is closed short. Cancelling it, withdrawing it or cancelling its order cancels it. [*] --> Open: Record rejection Open --> Resolved: Its extra work is done, or the order closed short Open --> Cancelled: Cancel, withdraw, or the order cancelled
| Status | How a rejection gets it | How it leaves it | Elsewhere |
|---|---|---|---|
| Open | Record rejection | Its extra work is done, the order is closed short, or it is cancelled | Its extra work is planned; its order doesn’t complete |
| Resolved | Its extra work made the rejected quantity, or the order was closed short | Never | Its leftover extra work is cancelled |
| Cancelled | Cancel QA rejection, Withdraw, or its order cancelled | Never | Its extra work leaves the plan |
The extra work is still to do. Every plan plans it, and the order can’t complete: completing the order by hand is refused until the extra work is done or the rejection is cancelled.
Resolved
Section titled “Resolved”The extra work made the rejected quantity, less what that work scrapped, and the rejection resolved by itself. Its tasks still open are cancelled, and a replacement on an order already received puts its output into stock. Closing the order short resolves its open rejections too. A resolved rejection can’t be cancelled.
Cancelled
Section titled “Cancelled”The rework or replacement won’t be done. On the order’s page, under QA rejections, Cancel QA rejection on an open row cancels it once you confirm; it needs schedule:write. Withdraw on its exception cancels it too, and cancelling the order cancels all its open rejections. Its tasks leave the master plan, with any work running on them, and a replacement’s material is no longer reserved. A write-off already made stays.
Still stuck? Write to support@example.com.