How werkplan's planner decides

Available on
  • Trial
  • Pro
  • Enterprise
Who can do this
  • Solve a scenario or the re-planRoles: AdministratorPermission: planning:execute
  • Add a production order with its due date and priority, or move it on the production sequenceRoles: AdministratorPermission: order:write
  • Publish the workforce scheduleRoles: AdministratorPermission: schedule:publish

werkplan’s planner places as much work as it can, then keeps rush orders on time, then keeps the other orders as little late as their priority asks. Only when two plans are equal on all of that does it prefer the one that ends sooner, then the one that keeps less work waiting, then the one that follows your Production sequence best.

werkplan’s planner compares two plans in this order. A later point counts only when the two plans are equal on every point before it.

Rank It prefers the plan that What this means for you
1 places the most operations Work is left out only when the planner can’t place it, such as a step no machine can run, or work already planned leaving it no room.
2 has the fewest minutes of lateness on rush orders A rush order is on time first, however many other orders that makes late.
3 has the least weighted lateness Each order’s minutes late count by its priority: Low once, Normal 4 times, High 9 times, Rush 16 times.
4 ends soonest The last operation of the plan ends as early as it can.
5 finishes each operation soonest Work is done early and little sits waiting between steps.
6 follows the production sequence best The order you put on the Production sequence screen holds where nothing above asks otherwise.

Lateness counts in working minutes on your calendar: an order finished first thing after a night off is a few minutes late, not a night late.

A due date is the end of its day in your organisation’s time zone. It is optional: an order without one is planned as early as the dated work allows, and it is never late.

Priority weighs lateness. Rush goes further: a rush order’s lateness ranks above every other order’s. Make an order rush only when it must be on time whatever else moves.

An operation starts only when everything it needs is free:

  • a machine that can run it, in a shift, outside the machine’s unavailable times;
  • the people trained for it, and the tools its routing step needs;
  • the step before it done, and the order’s sub-assembly orders finished;
  • the order’s earliest start, and the time its purchased material is there.

The material is there when it is in stock, from the start of the day after a purchase is expected, or, for material not ordered, from the start of the day after the supplier’s lead time has passed, counted from today. The Waiting for material list on the Master plan screen shows the orders it holds back.

People and the published workforce schedule

Section titled “People and the published workforce schedule”

Production plans against the published workforce schedule. Up to the day it is published through, an operation runs only in the published shifts of people trained for it, and the plan names who does it. After that day, or when nothing is published, the plan names nobody: it counts the trained people of each shift group evenly over the shifts the group runs, and plans as many operations as they can staff. You publish the workforce schedule on the Schedule screen.

When the planner can’t place an order at all, it leaves the whole order out and plans the rest. Unplannable orders lists each such order with the reason and what to do, such as Not enough tools or Not enough trained employees. The rest of the plan can still go into force.

A re-plan solved around a few exceptions moves other work only to place the work the exceptions free and to keep rush orders on time. When that leaves work with no room, it is solved in full instead. A full re-plan, solved beside it, ranks on every point, and you choose which of the two to promote.

How a scenario compares with the master plan

Section titled “How a scenario compares with the master plan”

Against the master plan on a solved scenario ranks it on the first points the planner ranks on, as far as the two plans can be compared: first the orders left out, then lateness on rush orders, then weighted lateness, then when the plan ends, with lateness in clock minutes. It says Better than the master plan, Worse than the master plan or Ranks the same as the master plan.

A solve takes a few seconds, and on a large plant up to about half a minute. You can leave the scenario’s screen while it solves: it carries on and saves its result. Nobody can lengthen a solve to get a better plan.